Los Osos Wastewater Project

Mission Statement: To evaluate and develop a wastewater treatment system for Los Osos, in cooperation with the community water purveyors, to solve the Level III water resource shortage and groundwater pollution, in an environmentally sustainable and cost effective manner, while respecting community preferences and promoting participatory government, and addressing individual affordability challenges to the greatest extent possible.


Collection System Construction

  Dig Los Osos Logo

 Visit DigLosOsos.com , a website developed specifically for the project collection system construction. DigLosOsos provided regularly updated schedules, maps of construction progress, information on expected traffic impacts, and contact information. With completion of pipeline installation, DigLosOsos is no longer being updated with new information.  However, information on the pipeline construction is still available to review.

 

The County is currently implementing a water conservation program, which includes  rebates for water saver fixtures.

Click here for a list of plumbers for the retrofit program (These plumbers are not pre-approved or pre-qualififed but have shown interest in the retrofit program).

Brochure  for Los Osos Water Conservation Rebate Program.

Visit the new website devoted to the Los Osos Water Conservation Rebate Program   http://conservelososos.org/

 

Questions?

Representatives from the County are available to help residents and businesses review lateral plans for their property, discuss costs, and answer any other questions regarding the Los Osos Wastewater Collection System Project.

Contact the County at (805) 788-2114 or rruiz@co.slo.ca.us with comments or questions, or to schedule an appointment. 

Note: Regular office hours will no longer be held at the 2025 10th Street office after May 29, 2014.

 

Recent News and Events 

September 25, 2014: Public Tour of the Water Recycling Facility construction site from 5pm to 6pm.  For more information and to sign up to attend, contact Rosalyn Piza at rpiza@co.slo.ca.us or (805) 788-2759. 

August 29, 2014: Project Construction Update for the month of July 2014.

July 31, 2014: Project Construction Update for the month of June 2014.

June 30, 2014: Project Construction Update for the month of May 2014.

June 27, 2014:  Baseline Groundwater Quality Report released to the Regional Water Quality Control Board. This was an additional requirement under the WDR R3-2011-0001. This report contains the latest Nitrate concentrations and Groundwater levels.

May 30, 2014: Project Construction Update for the month of April 2014.

May 22, 2014: Survey Report of the results of a telephone survey regarding awareness, participation, and compliance status with the water conservation program. The survey was conducted between April 29 and May 7. 

May 20, 2014: Board of Supervisors consent agenda Item 15 to authorize a change order for the Area B&C contract in the amount of $180,000 for additional collection system work. Read the staff report

April 29, 2014: Project Construction Update for the month of March 2014.

March 27, 2014Project Construction Update for the month of February 2014.

February 28, 2014: Project Construction Update for the month of January 2014.

February 26, 2014: The County staff conducted an Open House meeting in Los Osos to provide a project update. The meeting invitation was mailed to all residents and property owner with the date. The meeting was held at the Los Osos Middle School on February 26th.  A project update was provided including information on construction progress, schedule, water conservation program, costs, financial assistance planning, road improvements, and what to expect when connecting your lateral to the sewer system was presented. Watch the video. Powerpoint presentation.

February 21, 2014:  Baseline GroundwaterQuality Report released to the Regional Water Quality Control Board. This was an additional requirement under the WDR R3-2011-0001. This report contains the latest Nitrate concentrations and Groundwater levels.

February 3, 2014: Project Construction Update for the month of December 2013.


 

 

 

News Archives

 


 

librarypic

Application Picture

Board of Supervisors

FAQ3

Document Library

 

 

  Service Charges Ordinance

Board of Supervisors Items

 

 

FAQs

  Join our Mailing List  

Public Works is located in room 207B of the old Courthouse building,
Corner of Palm and Osos Streets in San Luis Obispo.
Office hours are Monday to Friday 8:00 AM to 5:00 PM
General information phone number is (805) 781-5252