Overall Project Description

The San Luis Obispo County Flood Control and Conservation District (District), in conjunction with the City of Paso Robles, Atascadero Mutual Water Company (AMWC), Templeton Community Services District (TCSD), City of San Luis Obispo, and County Service Area 10, Zone A (CSA 10A), has initiated the construction phase of the Nacimiento Water Project.  The Project has a construction value of approximately $125 million and will transmit raw water from Lake Nacimiento to communities within San Luis Obispo County. 

The Project's infrastructure consists of a 180-foot intake shaft and wetwell, 45 miles of pipe ranging from 36 inches to 12 inches, four turnouts, three pump stations, three welded steel strorage tanks, and a Supervisory Control and Data Acquisition (SCADA) system.

The Project is expected to be completed by December 2010.

 Spec Map

    

Contract Information

Spec 01 - Intake                                  Contract 300187.08.01                       Consists of intake facilities near the dam at Lake Nacimiento

Spec 02 - Facilities                              Contract 300187.08.02                      Consists of three pump stations, three tanks, and SCADA system at various locations along the pipeline alignment

Spec 03 - Pipeline North               Contract 300187.08.03                       Consists of 23 miles of pipeline from Lake Nacimiento to Paso Robles

Spec 04 - Pipeline Central      Contract 300187.08.04             Consists of 10 miles of pipeline from Paso Robles to Atascadero

Spec 05 - Pipeline South          Contract 300187.08.05                    Consists of 12 miles of pipeline from Atascadero to San Luis Obispo