Public Works will re-open our front counter to the public on July 6 and start providing some modified services.  Our hours will be 8 – 5, with closure from 12 – 1:30 for sanitation. Masks are mandatory in our building, and we ask that you adhere to physical distancing protocol. We will have limited services at our front counter and will not be accepting drop in meetings.  Please contact 805-781-5252 to make an appointment with staff.  Bus passes can be purchased at the Kiosk on the corner of Osos and Palm or by phone via slorta.org. Follow us on Twitter @SLOCountyPWD for the latest updates.

Return to the top of the page

Main Street at Highway 101 Interchange in Templeton

Goal: Reconfigure the interchange to provide traffic congestion relief while accommodating pedestrians and bicycles.

Estimated Cost: Current alternatives range from $15 million to $27 million.

Proposed Alternatives:

Project Contacts

For questions or additional information please contact Cori Marsalek via email or phone: (805) 781-4995.

Phase 1 - Project Initiation and Scoping

A Project Study Report was prepared by Caltrans to analyze various project alternative. Three project alternatives and a "no-build" alternative were determined viable options to carry forward for evaluation in Phase 2. The goal of this phase is to identify the project alternatives to be evaluated further in Phase 2. Funding for this stage consists of $250,000 from County Road Improvement Fees and $250,000 from San Luis Obispo Council of Government's Regional State Highway Account (RSHA) funds.

Estimated Date of Completion: July 2019

Phase 2 - Project Approval and Environmental Document

The goal of this phase is to evaluate the alternatives and obtain Caltrans approval. Funding for this stage consists of $750,000 from County Road Improvement Fees.

Estimated Date of Completion: 2022

Phase 3 - Design

The goal of this phase is to finalize the design. Funding is to be determined.

Estimated Date of Completion: 2024

Phase 4 - Construction

If funding is available and previous phases are completed on time, the earliest this project is anticipated to be in construction is in 2025. Funding is to be determined.

Estimated Construction “Shovel” Ready – 2025

Contact Public Works via web form, email, or call us at (805) 781-5252.