Public Works will re-open our front counter to the public on July 6 and start providing some modified services.  Our hours will be 8 – 5, with closure from 12 – 1:30 for sanitation. Masks are mandatory in our building, and we ask that you adhere to physical distancing protocol. We will have limited services at our front counter and will not be accepting drop in meetings.  Please contact 805-781-5252 to make an appointment with staff.  Bus passes can be purchased at the Kiosk on the corner of Osos and Palm or by phone via slorta.org. Follow us on Twitter @SLOCountyPWD for the latest updates.

Return to the top of the page

Contact Public Works via web form, email, or call us at (805) 781-5252.

New Probation Department Building

Description

This project will design and construct a new Probation Department office building to replace an ill-suited facility and serve the needs of a modern and growing County of San Luis Obispo Probation Department. The intent is to build a user friendly, accessible, safe, secure, and healthy environment for the Probation staff and the public.

Location/Conceptual Site Plan

The new building  will be sited on a portion of the twenty-one-acre County parcel located north of the Johnson Ave. and Bishop St. intersection in the City of San Luis Obispo.  The site is currently occupied by several existing Health Agency facilities which shall remain occupied during the construction. The new Probation Department building shall be located behind the existing facilities, on an undeveloped portion of the parcel and will take access from Bishop St.

Project Features and Benefits

  • Resolve significant inefficiencies of current, outdated main building and replace it with a new two-story 31,000+/- sf building that will be tailored to meet operational needs and will accommodate future departmental growth
  • Consolidate departmental functions at one location to allow shared operations and reduce intradepartmental travel
  • Upgrade department's physical infrastructure and systems to current state of the art
  • Improve convenience and access for public clients.

Project Contacts

For questions or additional information, please contact Rob Ruiz at [email protected], or Margaret Mayfield at [email protected].

Project Timeline

Estimated Completion dates for future Project Milestones:

Milestone  

Construction Manager / Master Architect Contract Award

September 2020

Development of Bridging Documents

January 2021

Design-Build Entities (DBE) Pre-qualification & Selection

September 2021

DBE Final Construction Documents

March 2022

Construction

June 2023