Search Start-up Phase

Forms & Documents > Projects > Nacimiento Water Project > Documentation > Start-up Phase

Name Description
2002 NWP Report on Recreational Use

Outlines the 2002 Recreational Use conditions at Nacimiento Lake based on existing codes, discussions with facility owners and operators, the Heritage Ranch CSD, and other resources available at the time.

2004 NWP Alignment Unit Map

Overview of the pipeline, river crossings, turnouts, and pump stations.

2007 NWP Environmental Impact Report Addendum

Addendum to the Final Project EIR completed in 2003.

2007 NWP Intake Facility

This paper discusses the planning and design of the intake facility.

2008 NWP Camp Roberts Finding of No Significant Impact

Analysis of the environmental assessment and the issuance of the finding of no significant impact.

2008 NWP Camp Roberts Report Of Availability

Construction and operations of the NWP through Camp Roberts, CA.

2008 NWP Environmental Assessment

This Environmental Assessment (EA) addresses the California Army National Guard’s issuance of a Report of Availability (ROA) of property on Camp Roberts Training Facility, California, to allow construction and operation of a water supply pipeline and storage tank within a proposed easement corridor.

2008 NWP How a Small Agency Manages a Mega Pipeline Project A Success Story

This paper discusses how the District made this regional Project successful by overcoming existing political obstacles and mending community relationships.

2008 NWP Nacimiento Lake Tap

Overview of the Lake Tap options and design.

2009 NWP Achieving Sustainability by Designing for Efficiency

Overview of the sustainability aspects of the projects.

2009 NWP Bidding Strategies

This paper addresses the SLO County Flood Control and Water Conservation District's implementation of bidding strategies.

2009 NWP Design and Hydraulics

This paper describes the hydraulic design of the Project and related engineering elements of the Project design.

2009 NWP Hot Tap Construction of Lake Nacimiento

This paper is a case history of the Project and describes a Project overview, the design, the prequalification of the general contractors, the construction of the intake facility, and concludes with lessons learned on this challenging work.

2009 NWP One Project - 6 HDDs: The Nacimiento Water Project

This paper describes the pre-qualification process used to identify eligible HDD subcontractors, the project’s environmental permit requirements, the physical designs unique to the project’s construction, and construction performance case history for those HDDs completed prior to final submittal of this paper.

2010 NWP Transient Pressure Monitoring

This paper describes the Nacimiento Water Project, the hydraulic design considerations, the network of transient monitoring systems that is installed, and construction considerations.

2011 NWP Alternatives for Pipeline Expansion

This Technical Memorandum is meant to develop alternative methods for incorporating future turnouts in the NWP.

2011 NWP Mercury Fact Sheet

Fact Sheet on the Mercury Issue at Nacimiento Reservoir.

2011 NWP NAEP Paper

Managing compliance with environmental permit conditions on a 45-mile pipeline in California: problems and solutions.

2011 NWP Recreation Report Update

Update on the 2002 Report, outlining the Nacimiento Water Project, the County of SLO and Monterey policies, and the changing lakeside communities impact on the lake.

2011 NWP Transient Pressure Monitoring Results

This paper describes the Nacimiento Water Project, the hydraulic design considerations, the network of transient monitoring systems that is installed, construction considerations, lessons learned, and the results of transient pressure monitoring collected during initial startup and testing.