Avila Beach Drive at Highway 101 Interchange

Project Updates

Environmental Document

The 30-day review and comment period for the proposed Mitigated Negative Declaration begins on January 6, 2020 and ends on February 5, 2020. Written comments must be received by 5:00 P.M. on the last day of the review period and should be addressed to: Matthew Willis, Environmental Specialist, [email protected], County Government Center, Room 206, San Luis Obispo, CA 93408.

Avila Valley Advisory Council Meetings

January 13, 2020 - Avila Valley Advisory Council meeting (Invitation) (Project Comments/Responses)

November 14, 2022 - Avila Valley Advisory Council meeting

Project Benefits

The five-legged intersection of the southbound ramp, Avila Beach Drive, and Shell Beach Road experiences significant congestion during peak hours, especially during weekend peak period. The general increase in traffic, coupled with the anticipated future traffic from planned projects in the area, is forecast to degrade this intersection to a Level Of Service 'F' by 2032. To reduce this congestion and maximize efficiency, the project will:

  • replace the stop-controls at the southbound ramp and Shell Beach Road intersection with a single-lane roundabout
  • install traffic calming features approaching the roundabout, including along the northbound off-ramp
  • provide a park-and-ride lot with bus stop

Estimated Construction Cost: $9 million to $13 million

Project Timeline

Project Contacts

For questions or additional information please contact the Project Manager, Aaron Yonker, PE via [email protected] or phone: (805) 781-4644.

Phase 1 - Project Initiation and Scoping - Complete

The completion of this project initiation phase establishes the project's purpose & need, provides scope approval, and allows for project development to begin. For more information see the PSR-PDS.

Date of Completion: May 2016

Phase 2 - Project Approval and Environmental Document

Completion of this project approval phase completes the required environmental documents and allows final design phase to begin. For more information see PA&ED.

Date of Completion: June 2020

Phase 3 - Final Design

The goal of this phase is to finalize the design. Funding for this stage consists of approximately $950,000 regional federal funds.

Estimated Date of Completion: Spring 2023

Phase 4 - Construction

Following the completion of the Final Design Phase, this project will be publicly bid for construction. It is anticipated that a contract will be awarded by late Summer 2023, initiating the Construction Phase.

Estimated Date of Completion: Summer 2025

Contact Public Works via web form, email, or call us at (805) 781-5252.