Probation Department Building

Description

This project will design and construct a new two-story, 34,000 sf building that will be tailored to meet operational needs, accommodate future departmental growth, provide state of the art technology and infrastructure and improve convenience and access for public clients. The intent is to build a user friendly, accessible, safe, secure, and healthy environment for the Probation staff and the public.

Location/Conceptual Design

The new building  will be sited on a portion of the twenty-one-acre County parcel located north of the Johnson Ave. and Bishop St. intersection in the City of San Luis Obispo.  The site is currently occupied by several existing Health Agency facilities which shall remain occupied during the construction. The new Probation Department building shall be located behind the existing facilities, on an undeveloped portion of the parcel and will take access from Bishop St.

Project Contacts

For questions or additional information, please contact Shelly Cone at [email protected]


Project Timeline

Receive Site Grading Permit: May 2024

Begin Site Development: June 2024

Submit Building Plans for Permitting: April 2024

Receive Building Permit: October 2024

Complete Construction: January 2026 (estimated)


Construction Progress Update

Completed Work

• Double check valve assembly installation, flushing and testing for fire, domestic, and irrigation water lines

• Irrigation main line installation

• Roof curb installation for HVAC split systems

• Main switchgear installation for building


Ongoing Work

• Metal stud installation of interior and exterior walls; gypsum sheathing placement around HVAC ductwork on first and second floors, and on exterior walls

• Domestic water and hydronic pipe installation, rain leader and condensate line placement, and plumbing fixture rough-ins on first and second floors

• HVAC ductwork installation on first and second floors

• Electrical hanger rod, conduit, and box placement on first and second floors

• Single ply roof system installation

• Formwork, steel reinforcement and concrete placement for exterior stairs


Upcoming Work

• Gypsum board installation for interior walls.

• Waterproof system installation for exterior walls with rigid insulation.

• Paper, lath and membranes installation for exterior stucco.


Construction Progress Photos

Southwest building exterior with substrate sheathing (Densglass) in place.


PVC roofing system installation, laid out on southwest side of roof, consists of polyvinyl chloride (PVC) sheeting rolled over a substrate of rigid 2-inch foam insulation. This highly reflective surface combined with the layer of insulation greatly reduces heat absorption.


Northwest building exterior. Telescoping boom lift is employed to access top of wall and install parapet cap.


Second floor open office space. Ongoing installation of ceiling insulation; HVAC ducts on the floor await installation.


Project Updates

June 3, 2024

Construction work commences.


May 23,2024

Grading Permit received from County Building Department.


April 2, 2024

Building Plans submitted to County Building for permitting.


December 8, 2023

Site Plans were submitted to the Building Department for plan check review to receive a Grading Permit.


March 10, 2023

The official 'Notice to Proceed' was issued to F&H Construction to commence the work for the final design and construction of the Probation Department Building. 


January 24, 2023

The County Board of Supervisors approved the award of the Design-Build contract for the final design and construction of the New Probation Department Building to F&H Construction.


October 18, 2022

The County concluded the evaluation process for the Proposals received from the short-listed Design-Build Entities and issued the Notice of intent to Award the Design-Build contract to F&H Construction from Lodi, CA.


June 7, 2022

The County released the Request for Proposals to the three pre-qualified Design-Build Entities shortlisted through the County’s Request for Statement of Qualifications process, and who are interested in designing and constructing the County’s New Probation Department Building. The County will receive Proposals on September 15th, 2022 and will be Scoring and Qualifying firms to get to the top-ranked Proposal and Design-Build Team by mid-November.