Sheriff’s Nipomo Substation

To contact the Sheriff’s Office:

For emergencies, please call 911.

For non-emergencies, please call Sheriff’s Dispatch at (805) 781-4550

Project Location

The project is situated on two County-owned parcels, located east of the 101 Freeway and directly north of the intersection of Tefft Street and Carrillo Street, within the unincorporated community of Nipomo.



Project Schedule

  • October 2024

Award Master Architect Contract (Board Action)

  • October – November 2024

Advertise Request for Statement of Qualifications to Interested Design-Build Entities

  • January 2025

Identify Top Ranked Design-Build Entities

  • July 2025

Bridging Documents Complete

  • August 2025

Issue Design-Build Request for Proposal to Top Ranked Design-Build Entities

  • February 2026

Award Design-Build Contract & Budget Adjustment (Board Action)

  • November 2024 – Late 2025

Environmental Review

  • Spring 2026 – 2027

Design and Permitting

  • Spring 2027

Start Construction (after rainy season)

  • Summer 2028

Project Completion