Nacimiento Pipeline Unit G Repair
What's HappeningThe pipeline currently sits in a flood-prone area and this project moves the pipeline to a safer location to:
| Project Status: Final Design Tree Trimming and Removal Start: Fall 2026 Construction Start: Spring 2027 Duration: ~6–8 months total This page will be updated regularly with construction schedules, road impacts, and notices. |
Completed Milestones
- January 9, 2023 – Nacimiento Water Project Pipeline collapsed into the Salinas River after heavy flooding.
- January 9, 2023 – The Emergency Services Director issued a Proclamation of Local Emergency.
- January 14, 2023 – A Presidential major disaster, CA-4683-DR, was declared for the State of California on January 14, 2023, for severe winter storms, flooding, landslides, and mudslides occurring beginning December 27, 2022.
- January 17, 2023 – San Luis Obispo County was added to Presidential Disaster Declaration CA-4683-DR through Amendment No. 1.
- January 24, 2023 – The Board acting as the Board of Supervisors for the San Luis Obispo Flood Control and Water Conservation District reviewed, ratified and approved the emergency actions needed to repair the Nacimiento Water Pipeline.
- March 2023 – The District hired an engineering consultant to analyze Nacimiento Water Pipeline repair alternatives and design the selected alternative.
- August 24, 2023 – Repair Alternatives were presented to the Nacimiento Commission. The Nacimiento Commission recommended that staff proceed with delivering the proposed realignment project.
- November 2023 – Right of Entry Agreements obtained from impacted property owners for survey and geotechnical investigations to support the proposed realignment project.
- February 22, 2024 – The Nacimiento Commission recommended that the Board authorize a budget adjustment in the amount of $1,038,000 to complete design and planning for the realignment project.
- October 2024 – Notification was sent to Salinas Road residents regarding the proposed realignment project and planned geotechnical investigations on Salinas Road.
- June 2024 – The Board acting as the Board of Supervisors for the San Luis Obispo Flood Control and Water Conservation District approved the Nacimiento Water Project Fiscal Year 2024-25 Budget, which included $8,292,000 for funding final design and construction of the realignment project.
- June 2024 – Staff conducted site visits with permanent easement property owners.
- May 2025 – Environmental Impact Report amendment finalized.
- May 2025 – Initiated easement acquisition discussions and negotiations.
- May 13, 2025 – Chia Lane community meeting held. Staff met with Chia Lane residents to share proposed project plans, potential community impacts and access options.
- June 6, 2025 – Draft Final Design completed.
- June 17, 2025 – Salinas Road community meeting held. Staff met with Salinas Road residents to share proposed project plans, inform residents that construction of the project will require limiting access to properties, and collect feedback in order to find ways to reduce those impacts.
- August 13, 2025 – Chia Lane site visit completed. Staff met with Chia Lane residents to review site conditions.
- September 2025 to June 2026 – Easement discussions and negotiations continued.
- July 9, 2026 – The Nacimiento Commission approved and recommended that the Board subsequently approve several settlements and agreements associated with the acquisition of easements needed for the pipeline realignment project.
Next Milestones
- August 2026 – The District Board will review and consider approving several settlements and agreements associated with the acquisition of easements needed for the pipeline realignment.
- September - February 2027 – Salinas Road Tree Removal and Trimming.
- May 2027 – Target construction start.
- December 2027 – Target construction completion.
- 2027-2033 – Target environmental mitigation.
Stay Updated
Bookmark this page for:
- Project updates
- Road closure notices
- Schedule changes
Project Contacts
Nola Engelskirger, Water Utilities Division Manager(805) 788-2100
[email protected]
Anna McKenna, Supervising Engineer
(805) 781-1521
[email protected]
FAQs
Placement of the Pipeline in Salinas Road will relocate this portion of pipeline out of the flood plain, reducing the likelihood of future failures due to flooding. The District evaluated alternative routes, but Salinas Road was ultimately chosen because it best meets the project goals and improves long term resiliency of the Nacimiento Pipeline.
In addition, Salinas Road is an original Atascadero Colony road, over which the County of San Luis Obispo has received and accepted an offer of dedication for an easement per Board Resolution in 1993. The properties along this segment of Salinas Road are subject to this easement.
