Interceptor Bypass Project

This map shows the location of the interceptor sewer pipelines (beneath Lake Nacimiento) for the CSA 7A wastewater collection system and Lift Station No. 3


Project Purpose

The CSA 7A Oak Shores - Interceptor Bypass Project is intended to reduce vulnerability of the existing CSA 7A wastewater collection and treatment system to damage and leakage and to reduce the associated potential risk to public health and safety from potential sewer spills that could impact Lake Nacimiento, a regional drinking water source and recreation body of water. This project focuses on bypassing a majority of the sewer pipeline located below the high-water line of the lake. The risk of a sewer spill has significantly increased because soil erosion has exposed much of the pipeline along the lake, impacting the supporting structure for the pipes and leaving it unprotected to hazards such as wake action and corrosion.

 

Project History

Check out the full timeline below by expanding each year.

1970-1971
1973
1976
1988
2003
2004
2011
2013
2015
2021
2023
2025
Oak Shores, California – The westside interceptor sewer pipeline shown in blue with the exposed segments shown in red (ref: 2015 Risk Analysis Study)

Project Elements

The Interceptor Bypass Project includes several key elements designed to improve system performance and reliability. These include installation of a new bypass pipeline, construction of new maintenance access structures, and upgrades to existing infrastructure to handle future capacity needs. Together, these improvements will enhance operational flexibility and reduce the risk of service interruptions.

Find out more

Special Considerations for the Project

Lake Nacimiento serves as both a regional drinking water source for the cities of Paso Robles, Templeton, Atascadero and San Luis Obispo and as a recreational body of water for uses such as boating, fishing, and swimming. There are two existing boat launch ramps at the Oak Shores Resort and other ramps located around the lake shores. Completing this project would continue to ensure public health and safety for all the users and uses of Lake Nacimiento.


The interceptor sewer pipelines are located below the high-level of the lake, and so construction activities will need to consider factors related to working within the lake including coordinate with lake users and uses, timing on the water levels, and activities to be done within jurisdictional waters, all of which increase the complexity and cost of the project. For example, the project will require special permits from federal agencies like the Army Corps of Engineers.

 

Project Timeline

YearActions
2025
  • Feasibility Study completed
  • Initiate funding study
  • Begin public outreach
  • Begin seeking grant/loan opportunities
  • Begin easement acquisitions
  • Complete Element 1 65% design
  • Begin preparing environmental documents
  • Initiate design activities for Elements 2 and 3
2026
  • Complete funding study and voter approval
  • Complete Element designs for:
    • Sewer Bypass
    • Pipe Rehabilitation
    • Lift Station #3
  • Secure interim construction loan
  • Apply for grant opportunities
  • Complete easement acquisitions
  • Complete environmental documentation and permitting
2027
  • Prepare bid documents and award contracts
  • Coordinate with MCRWA on lake levels and access
  • Begin construction activities when conditions allow
2031
  • Completion of construction activities
  • Conversion of interim loans to long-term USDA loans

Grant Opportunities and Efforts 

TThe County has secured $4 million in American Rescue Plan Act funding for CSA 7A, including $1.25 million dedicated to the design of Element 1. To help offset project costs, the County will continue exploring additional grant opportunities. Once the design phase is complete, additional grant applications can be submitted. In the meantime, we have developed an informational funding sheet to raise awareness with potential grantors.


Current Estimated Interceptor Project Cost

Estimated Cost
Project Element
$20M - $24M

Element 1 - Interceptor Sewer Pipeline Bypass and Abandonment

$6M - $8M

Element 2 - Interceptor Sewer Pipeline Rehabilitation

$1M - $2M

Element 3 - Lift Station No. 3 Coating

$5M - $7M

Estimated Debt Service

$32M - $41MTotal Estimated Project Cost
Project Funding